Project Change Request Template

Use this when a request may add, remove, exchange, or defer work covered by an existing project. First decide whether the request is a correction under the agreement or genuinely changed scope.

Source: assistedfreelance.com/templates/project-change-request

Context and limits

Before you use it

  • Reference the accepted scope and quote the relevant baseline accurately.
  • Do not begin changed work until the agreement’s required approval step is complete.
  • A change can affect dependencies and acceptance criteria even when its immediate fee is zero.

Blank reusable version

Copy, edit, and verify.

# Project Change Request

## Project and original scope reference
[Project name, agreement/SOW reference, date, and relevant original scope.]

## Requested change
[Describe the request in neutral, concrete terms.]

## Reason for the request
[Business, user, technical, or scheduling context.]

## Work added, removed, exchanged, or deferred
Added: [work]
Removed: [work]
Exchanged or deferred: [work]

## Price and expense impact
[Added credit or fee, currency, expenses, invoice/payment trigger, or no-price-impact explanation.]

## Schedule impact
[Changed milestones, delivery date, review window, or no-impact explanation.]

## Dependency and responsibility impact
[New content, access, people, decisions, third parties, or risks.]

## Acceptance impact
[New or changed deliverables, tests, approver, and acceptance criteria.]

## Decision
[Approve / decline / revise / defer, plus any conditions.]

## Approval and effective date
[Authorized names, roles, approval method, date, and when changed work may begin.]

Completed fictional example

Two additional bakery landing pages

Use this to understand the level of specificity, not as facts, pricing, tax treatment, or agreement wording for your project.

# Project Change Request — HSB-WEB-01-CR02

## Project and original scope reference
Harbor Street Bakery website, SOW HSB-WEB-01. Original scope: five responsive pages; campaign landing pages excluded.

## Requested change
Add two responsive landing pages for Wedding Catering and Corporate Catering using the approved visual system.

## Reason for the request
The bakery decided to separate two catering audiences after the site structure and original design direction were approved.

## Work added, removed, exchanged, or deferred
Added: two landing-page layouts, build, supplied-content entry, navigation links, and agreed checks. Removed: none. Deferred: none.

## Price and expense impact
Additional fixed fee: $1,200 USD, invoiced 50% on change approval and 50% after acceptance. Entirely fictional figures; tax treatment and actual payment rights come from the applicable agreement and law.

## Schedule impact
Move the target launch from November 21 to December 2, subject to approved copy arriving by November 8 and consolidated feedback within three business days.

## Dependency and responsibility impact
Sam supplies approved copy and images for both pages. Jordan confirms whether existing licensed assets cover the added use.

## Acceptance impact
Both pages use approved copy, link from the agreed navigation, pass the project’s mobile/desktop, keyboard, browser, and accessibility checks, and route inquiry links correctly.

## Decision
Approved as written. The original five-page scope remains unchanged except for the additions and dates stated here.

## Approval and effective date
Sam and Jordan approve through the method required by their agreement on [date]. Added work begins only after that approval and the first change payment trigger are satisfied.

Field by field

Adapt it deliberately

Baseline
Identify the exact scope or requirement being changed so the comparison is traceable.
Changed work
List added, removed, exchanged, and deferred items rather than recording only the new request.
Price and schedule
Show credits, fees, expenses, milestones, and dependency-driven date changes.
Responsibilities
Name new inputs, access, approvals, and third-party decisions.
Acceptance
Update observable checks to match the changed result.
Authority
Follow the actual agreement’s approval method and state when work may begin.

Important considerations

Common mistakes

  • Do not use a change request to charge for correcting work that already fails the accepted criteria.
  • Do not describe only the fee; record schedule, responsibility, and acceptance effects as well.
  • Do not treat silence or an informal suggestion as approval when the agreement requires something else.